Published on
9 August 2024
Status
Completed

Queensland Betterment Fund, investing to create stronger, more resilient Queensland communities

Expected duration
Jun 2013 - Jun 2025
SFVC commitment ID
20221114_004
Version
4.0
Author
Jimmy Scott
Upload your content

Queensland leads the nation in delivering betterment programs that demonstrate how upfront investments in stronger, more resilient assets, saves money for all levels of government in future disasters.

    Description

    QRA is responsible for managing and coordinating the Queensland Government’s program of infrastructure renewal and recovery within disaster‐affected communities, with a focus on working with our state and local government partners to continue to deliver best practice administration of public reconstruction and resilience funds.

    Examples of betterment include improvements to vital infrastructure such as roads, bridges and floodways. These improvements can vary from stabilisation of low-lying roads to reduce erosion and scouring, upgrades to drainage structures to increase capacity or replacing gravel with reinforced concrete to improve resilience.

    Queensland Betterment Funds are jointly funded (50:50) by the Australian and Queensland Governments.

    Under the program there have been six separate betterment programs:
    • 2022 Central, Southern and Western Queensland Rainfall and Flooding; Ex-Tropical Cyclone Seth Flooding; and the South-East Queensland Heavy Rainfall and Flooding event $170 million Betterment Fund
    • 2021 (2020-21) disaster season $20 million Betterment Fund
    • 2019 North and Far North Queensland Monsoon Trough $102 million Betterment Fund (delivered)
    • 2017 Severe Tropical Cyclone Debbie $41.85 million Betterment Fund (delivered)
    • 2015 Severe Tropical Cyclone Marcia $20 million Betterment Fund (delivered)
    • 2013 Severe Tropical Cyclone Oswald $80 million Betterment Fund (delivered).

    Did the Sendai Framework change or contribute to changes in your activities/organization? If so, how?

    The Sendai Framework continues to assist in setting policy context for these programs, encouraging investment in disaster risk prevention to improve project outcomes and Queensland’s future resilience to disasters.

    The continued influence of the Sendai Framework is highly prevalent in the development of these programs and more broadly, highlighted in the Queensland Strategy for Disaster Resilience (QSDR) 2022-2027, which identifies strategic commitments that will embed disaster risk reduction and resilience into decision making. The QSDR is aligned to international best practice, including the Sendai Framework, promoting opportunities to build resilience across Queensland.

    What led you to make this commitment/initiative?

    What was your position before making this Voluntary Commitment / prior to the Sendai Framework?

    QRA is the state’s lead agency responsible for disaster recovery and resilience policy in Queensland. The Queensland Government is committed to strengthening disaster resilience to ensure communities are better equipped to deal with the increasing prevalence of disasters.

    Prior to the creation of the Betterment program, projects were being repaired without emphasis on the need to make them more resilient to future potential disasters. Therefore, the approach to reconstruction needed to change and the focus moved to betterment.

    Through making this commitment, QRA will be able to share our learnings in relation to betterment programs, demonstrate the importance of investment in resilience, and highlight our progress with the international community.

    Deliverables and Progress report

    Deliverables

    Deliverables are the end-products of the initiative/commitment, which can include issuance of publications or knowledge products, outcomes of workshops, training programs, videos, links, photographs, etc.

    2013 Severe Tropical Cyclone Oswald $80 million Betterment Fund.
    Intended date of delivery
    1 June 2015

    232 projects across 35 local government areas were approved.

    Project Highlight: Gayndah Mundubbera Road

    Gayndah Mundubbera Road is an essential freight and transport link for the North Burnett region. The road was damaged in 2011 and rebuilt only to be re-damaged in 2013. Betterment funding from 2013 was used to increase the resilience of the two-kilometre section of road adjacent to the Burnett River that was washed out, relocating it 11 metres uphill. New stormwater drainage works (including concrete lined channels, culverts and scour protection) were also completed, improving functionality of the entire Gayndah Mundubbera Road.

    The road has since been impacted by seven natural disaster events (one in 2015, one in 2016, two in 2017 and three in 2022) and has remained functional with only minor expenditure required to clean up and remove debris.

    Link
    https://www.qra.qld.gov.au/betterment/betterment-in-action#Gayndah-Mundubbera-R…
    2015 Severe Tropical Cyclone Marcia $20 million Betterment Fund.
    Intended date of delivery
    1 June 2017

    58 projects across 8 local government areas were approved.

    Project highlight: Scenic Highway

    Scenic Highway suffered major landslips and severe erosion at Statue Bay during Severe Tropical Cyclone Marcia in 2015.

    The highway is the key link between Yeppoon and communities along Keppel Coast. It provides key access to tourism and boating facilities at Rosslyn Bay - the only access to the Keppel Islands and the Great Barrier Reef from Central Queensland.

    The work was a complex balance between sensitivity and engineering as it is adjacent to delicate marine ecosystems in a challenging location with exposed coastal conditions. It was also a complex geotechnical site, with a steep cliff face to the east with residents atop, and a severely damaged downslope interfacing with both sand and rock. Council was approved for a NDRRA Category D Betterment project to restore and increase the resilience of the road at the impact site and reopened the road on July 2018.

    Link
    https://www.qra.qld.gov.au/news-case-studies/case-studies/livingstone-builds-ba…
    2017 Severe Tropical Cyclone Debbie $41.85 million Betterment Fund.
    Intended date of delivery
    1 June 2019

    83 projects across 22 local government areas were approved.

    Project highlight: Shute Harbour Restoration

    Shute Harbour in the Whitsunday Regional Council area was significantly damaged as a result of Severe Tropical Cyclone Debbie in late March 2017.

    QRA also secured three extensions of time for the project , extending the allowable time limit until 31 December 2021, and approved final budget for costs under the NDRRA of approximately $60 million with Council also contributing to the project.

    Following demolition works, construction of the new marine facility commenced in February 2021. Not only has the project seen the complete rebuild of the terminal facility, the finger wharves and the ferry pontoons, a discreet $1.8 million Betterment project to raise the height of the seawall by up to a metre, helping to protect the new facility against future cyclonic events.

    Link
    https://www.qra.qld.gov.au/news-case-studies/news/shute-harbour-marine-terminal…
    2019 North and Far North Queensland Monsoon Trough $102 million Betterment Fund.
    Intended date of delivery
    1 June 2021

    107 projects across 35 local government areas were approved.

    Project highlight: Sedan Dip Road

    Sedan Dip Road in Cloncurry Shire in remote north western Queensland has been rebuilt better than ever after it was damaged by the monsoon and floods in February 2019.
    The road works received $9.4 million in Betterment funding under the joint Commonwealth and Queensland Governments Disaster Recovery Funding Arrangements. Sedan Dip Road provides essential access for livestock from major pastoral operations across two shires.

    This betterment funding has allowed Cloncurry Shire Council to increase the longevity of the road, giving primary producers the ability to move to and from their properties as required.
    The Betterment upgrade works will also provide the remote communities of Cloncurry and McKinlay access to vital services in the event of a crisis.

    The Betterment Funding created construction jobs as well as improving the safety and efficiency of The Sedan Dip Road many times over.

    Link
    https://www.qra.qld.gov.au/news-case-studies/case-studies/sedan-dip-road-cloncu…
    2021 (2020-21) disaster season $20 million Betterment Fund.
    Intended date of delivery
    1 March 2024

    The Queensland Government has established a $20 million Betterment Fund that will be available in 47 local government areas in Queensland impacted in the 2020-21 disaster season. It is jointly funded by the Australian and Queensland governments.

    Link
    https://www.qra.qld.gov.au/betterment2021
    2022 Rainfall, Flooding And Ex-Tropical Cyclone $170 million Betterment Fund
    Intended date of delivery
    1 March 2025

    The Queensland Government has established a $170 million Betterment Fund ($150 million under DRFA Category D and $20 million DRFA Category E) that will be available across local government areas in Queensland impacted in the 2021-22 disaster season. It is jointly funded by the Australian and Queensland governments.

    Link
    https://www.qra.qld.gov.au/betterment/2021-22-betterment-fund-170-million

    Porgress report

    Progress date
    1 October 2023
    Summary

    DELIVERABLE FIVE: 2021 (2020-21) disaster season $20 million Betterment Fund.
    The Queensland Government has established a $20 million Betterment Fund that will be available in 47 local government areas in Queensland impacted in the 2020-21 disaster season.

    There are 38 projects across 20 councils that have been approved and are in delivery. Just over $8.8 million has been approved for betterment projects in 8 Aboriginal and Torres Strait Islander Local Government Areas.
    DELIVERABLE SIX: 2022 Rainfall, Flooding and Ex-Tropical Cyclone $170 million Betterment Fund
    The Queensland Government has established a $170 million Betterment Fund that will be available across local government areas in Queensland impacted in the 2021-22 disaster season.

    There are 44 approved projects across 20 Local Government Areas and the Department of Transport and Main Roads. These projects total a value of $52.4M (as of 11 July 2023). This program has been oversubscribed due to high demand.

    Achievements at a glance

    Of the 531 betterment projects completed to date, 423 projects have been subsequently impacted a total of 1173 times across 44 events. An interactive map on Betterment projects is available on the QRA website - https://www.qra.qld.gov.au/betterment/betterment-projects-interactive-map-and-list

    79 per cent of those impacted suffered no damage, or only minor superficial damage. From a $174 million investment, there is $397.5 million in avoided reconstruction costs*.

    *Avoided costs are estimates only, based on data provided by councils on impacts or likely impacts, and calculated on eligible reconstruction costs under Category B of the Disaster Recovery Funding Arrangements / Natural Disaster Relief and Recovery Arrangements at the time of project approval. Information is current as of July 2023.

    Organizations and focal points

    Implementing Organization(s)

    • Queensland Reconstruction Authority

    Focal points

    Main focal point
    Jimmy Scott (General Manager, Resilience, Queensland Reconstruction Authority)

    Partners

    • Queensland Government

    Explore further

    Sendai priorities
    Priority 3Investing in disaster risk reduction for resilience
    Priority 4Enhancing disaster preparedness for effective response, and to «Build Back Better», rehabilitation and reconstruction
    Sendai targets and indicators
    B-5Number of people whose livelihoods were disrupted or destroyed, attributed to disasters
    C-3Direct economic loss to all other damaged or destroyed productive assets attributed to disasters
    C-5Direct economic loss resulting from damaged or destroyed critical infrastructure attributed to disasters
    D-4Number of other destroyed or damaged critical infrastructure units and facilities attributed to disasters
    D-6Number of disruptions to educational services attributed to disasters
    D-8Number of disruptions to basic services attributed to disasters
    Hazards Avalanche Cold Wave Cyclone, Hurricane and Typhoon Drought and Desertification Earthquake Flood Heatwave and Extreme Heat Landslide Storm surge Tornado Tsunami Volcano Wildfire
    Themes Critical infrastructure Recovery Structural safety
    Country and region Australia
    Sustainable Development Goals SDG9: Industry, innovation and infrastructure SDG11: Sustainable cities and communities
    Budget scale
    More than USD 5 million
    Scope
    National (or local) - Australia
    Scale of beneficiaries
    More than 10,000 people
    Estimated number of beneficiaries
    5,000,000 people
    Secured budget size
    100%
    X (Twitter)
    https://twitter.com/qreconstruction
    Related links
    QRA Linkedin
    Queensland Reconstruction Authority
    Queensland Betterment Fund
    Interactive map of betterment funded projects

    Is this page useful?

    Yes No
    Report an issue on this page

    Thank you. If you have 2 minutes, we would benefit from additional feedback (link opens in a new window).

    PreventionWeb is the global knowledge sharing platform for disaster risk reduction (DRR) and resilience.

    • Newsletter
    • Submit your content
    • Blog pitches
    • Submission and publishing policy
    • About PreventionWeb
    • Contact us

    Hazards

    • Avalanche
    • Cold Wave
    • Cyclone, Hurricane and Typhoon
    • Drought and Desertification
    • Earthquake
    • Epidemic and pandemic
    • Flood
    • Heatwave, extreme heat and heat stress
    • Insect infestation
    • Land subsidence
    • Landslide
    • Nuclear, biological, chemical (NBC)
    • Sea level rise
    • Technological hazard
    • Thunderstorm
    • Tornado
    • Tsunami
    • Volcano
    • Wildfire

    Regions

    • Africa
    • Americas
    • Asia
    • Europe
    • Oceania

    Themes

    Understanding & managing risk

    • Preparedness
    • Early warning
    • GIS and mapping
    • Data and information management
    • Risk identification and assessment
    • Small Island Developing States
    • Earth Observation

    Natural environment

    • Climate change
    • Environment and ecosystems
    • Food security and agriculture
    • Water

    Cross-cutting

    • Systemic risk
    • Recovery

    Human development

    • Capacity development
    • Children and youth
    • Civil society / NGOs
    • Community-based DRR
    • Cultural heritage
    • Gender
    • Human mobility
    • Inclusion
    • Social impacts and resilience

    Science, knowledge & advocacy

    • Disaster risk communication
    • Traditional and Indigenous knowledges
    • Science-policy-practice interface

    State, governance & economy

    • Financing DRR
    • Fragility and conflict
    • Governance
    • Insurance and risk transfer
    • Private sector

    Infrastructure & critical services

    • Critical infrastructure
    • Education and school safety
    • Health and health facilities
    • Structural safety